Albarrie Geocomposites Ltd. had the privilege to install our SorbWebTM Plus secondary oil containment system for TransCanada Pipelines. This is the first of many pump stations in the 12 billion dollar Keystone Project Pipeline being installed from Canada to the Gulf of Mexico. The site was located in a farmer’s field and would be isolated from urban contact so SorbWebTM Plus was therefore the best solution, as it is a maintenance free secondary oil containment system. The transformer at this site contained a considerable amount of oil at 9,570gals or 36,226 liters. The site also required drainage due to the soils being impermeable.

We start with the excavation and also build side slopes around the transformer at a 1:1 slope. This is done when the transformer pads are not as deep as the containment and we don’t want undercutting or erosion under the pad to occur.

We strap all the transformer pads with the impermeable liner by drilling through the plastic straps and hammering in a concrete anchor.

A 2”(50mm) base sand layer is placed on the floor of the containment and the drainage(wick drains) are laid out. The sand will aide in the drainage process.

Several types of connections are used with the wick drains, here we see a versatile connector that can be used as a ‘Y’ or a 90. The unused openings are taped over.

The lines are connected together and brought to an area where it exits the containment site. A minimum slope of 0.5% must be maintained for the system to properly drain.

We excavated through the bank to an existing gravel swale where the wick drains will drain. A minimum width of 18” (0.45m) is required.

A non woven geotextile is placed in the trench to prevent backfill from migrating into the system and the wick drain is laid in.

A washed crush stone is placed over the wickdrains. A minimum depth of 12”(0.30m) of stone is required.

The Oilmat edge is then sprinkled with loose copolymer(white powder) and is double beaded on the top side with the silicone sealant.

The top layer of impermeable liner is then folded down and glued to the Oilmat. An extra bead of silicone sealant is placed along the edge and then covered with the loose copolymer again.

In the case of conduits adjacent to the transformer pads we followed these steps. Strap up tight on either side of the conduits. Fill the hole with sand just below the level of the strapping.

Neatly cut a piece of impermeable liner to fit around the conduits and overtop of the liner that is already in place.

The containment is then filled with the designed required stone, in this case a minimum ¾” washed crush.

The containment is only filled up to a point below the strapping. We want to see if there is any pulling of the strapping off the walls. We then can do a final silicone bead along the impermeable liner attachment.

The containment is then filled to the design height with the rest of the stone and leveled off. As you can see it will stand up to a considerable amount of weight.

Here is the finished completed graded site and the entire containment system is non intrusive or even visible. It will protect the environment in the event of a catastrophic transformer failure for many years with no maintenance whatsoever.
Prepared by:
Michael J Dowds
of Albarrie Geocomposites Ltd.
Civil Engineering Technologist
T- (705) 737-0551
F- (705) 733-5053
www.sorbwebplus.com
www.albarrie.com






















